QUALITY MANAGEMENTS
MATERIAL TRACEABILITY
PROCESS
- SPECIFICATION & MILL CERT REVIEW BEFORE PROCUREMENTS
- MATERIAL RECEIVING INSPECTION
- HEAT NUMBER TRANSFER
- DATA RECORDING IN MDR (MANUFACTURER DATA RECORD BOOK)
WELD JOINTS & NDE TRACEABILITY
PROCESS
- PROJECT WELD JOINTS IDENTIFICATION ON DWG
- PROJECT WPS & WELDER QUALIFICATION REVIEW
- PROJECT NDE PROCEDURE REVIEW
- WELDING REQUIREMENTS BREIFING
- WELD JOINTS PREPARATION INSPECTION
- INSPECTION, TRACING & RECORD OF WELD JOINTS DATA (FIT UP DATES, WELDING START & END DATES, WELDER, WPS, WELDING PARAMETER, ETC)
- WELDING CONSUMABLE MANAGEMENT INSPECTION, TRACING & RECORD
- WELDING MACHINE MANAGEMENT INSPECTION, TRACING & RECORD
- THIRD PARTY NDE INSPECTION ARRANGMENTS AS RQEUIREMENTS
- DATA RECORDING IN MDR (MANUFACTURER DATA RECORD BOOK)
DIMENTIONAL TRACEABILITY
PROCESS
- DIMENSION REVIEW ON DWG, ESTABLISHMENT OF INSPECTION METHOD
- CARRY OUT DIMENTIONAL INSPECTION IN ACCORDING TO FABRICATION PLAN & DWG REQUIREMENTS (PRE-WELD)
- ALLOWANCES REQUIRE FOR WELDING SHALL CAPTURE AS REQUIRE
- CARRY OUT DIMENTIONAL INSPECTION IN ACCORDING TO FABRICATION PLAN & DWG REQUIREMENTS (POST-WELD)
- CARRY OUT DIMENTIONAL INSPECTION IN ACCORDING TO FABRICATION PLAN & DWG REQUIREMENTS FOR PARTS AFTER FABRICATION PROCESS (MACHINING / FORMING , ETC)
- DATA RECORDING IN MDR (MANUFACTURER DATA RECORD BOOK)
ALL OTHERS TRACEABILITY
PROCESS
- INDENTIFICATION OF PROJECT ACTIVITY INVOLVED, AND THE DATA RECORD AND TRACEABILITY RQUIREMENTS
- MDR SHALL INCLUDES BUT NOT LIMITED TO DATA AND TRACEABILITY FOR COATING, TESTING, HEAT TREAMENT, ETC (WHICH THE ACTIVITY IS PART OF THE PROJECT QUALITY)
- DATA RECORDING IN MDR (MANUFACTURER DATA RECORD BOOK)